We have made excellent progress with the conversion into 12 apartments ahead of schedule at our Palm Street Development in Nottingham.
Kitchens are going in on the second floor this week, and the first floor is getting plastered through.
Ground floor is around 4 weeks behind.
By the end of the month the render will be well underway outside.
On track to be completed by the end of October - an excellent 5-6 months from start to finish.